45 Projects under 11th RKN Completed

The Minister at the Prime Minister’s Office and Second Minister of Finance and Economy also shared that 45 projects have been completed physically under the 11th National Development Plan.

The completed projects are the Department of Sultan Omar Ali Saifuddien, upgrading Serasa industrial road leading to Pulau Muara Besar Port, construction of a flyover over Muara Tutong highway at Kampung Lugu junction, Kampung Lumut Drainage Scheme, Tutong River Flood Plain Repair Scheme, Improvement of BruHims system and construction of Sultan Hassan Bangar Secondary School. 75 projects are being implemented, among them infrastructure projects, while 91 projects are still in various stages such as planning, tendering and designing. 11 projects in the 11th NDP have been cancelled taking into account that seven would be implemented through Alternative Financing and four projects are no longer needed.

Source: Radio Television Brunei